Town of Parker

Project Size

$22,100,00.00

Completion

Originally bid for a 2 season contract, completed major roadway components in 1 season

Details

Construction crews pouring over 1,300 CY of bridge deck. 

Selling Points

Over 4,000 LF of new construction roadway from Dransfeldt Road to Twenty Mile Intersection. In additional of the connection of roads the bridge will cross over Cherry Creek that is environmentally sensitive. Because of our great relationship with owners and original bid price was able to add an additional $900,000 of additional work for items that the Town of Parker needed to complete.

Major Achievements

Originally bid for a 2 season contract, completed major roadway components in 1 season.

Savings

$1,000,000 because of SEMA’s aggressive bidding