Location
Milford, NE
Owner
Burlington Northern Santa Fe Railway
Project Size
$26,000,000
Details
Work consists of grading 6 miles of new second main tracking, including construction of 4 major bridges. The project task included constructing embankment, excavation, track bedding, drainage, concrete boxes, asphalt, road crossings, utility coordination and erosion control.
Selling Points
Constructing over 6 miles of new track with 4 major bridge structures.
Major Achievements
Critical pick plans on the brides based on height of bridge and weight of girders. In addition to having to work with the Army Corps of Engineers to construct a temp bridge to allow for access across the river.