Location

Milford, NE

Owner

Burlington Northern Santa Fe Railway

Project Size

$26,000,000

Details

Work consists of grading 6 miles of new second main tracking, including construction of 4 major bridges. The project task included constructing embankment, excavation, track bedding, drainage, concrete boxes, asphalt, road crossings, utility coordination and erosion control.

Selling Points

Constructing over 6 miles of new track with 4 major bridge structures.

Major Achievements

Critical pick plans on the brides based on height of bridge and weight of girders. In addition to having to work with the Army Corps of Engineers to construct a temp bridge to allow for access across the river.