Construction for this $63.7 million design-build project includes the removal and reconstruction of the interchange ramps and bridges for the following movements: Westbound S.R. 408 to Southbound S.R. 417, Eastbound S.R. 408 to Southbound S.R. 417, Northbound S.R. 417 to Westbound S.R. 408 and Southbound S.R. 417 to Eastbound S.R. 408. Post tensioning of curved concrete u-beams will be required for the new bridge structures. The project scope includes: roadway construction, bridge construction, storm drainage, signing, sign structures, pavement markings, lighting, fiber optic network, ITS devices, guardrail, retaining walls, noise walls; maintenance of traffic and including roadway, drainage, signing and marking, ITS, Lighting, retaining walls, and sound walls.